1Discharge
-no longer has duties under the contract.
-most contracts are discharged by full performance
2Rescind
Terminate a contract
3Strict Performance
Requires one party to perform its obligations precisely, with no deviation from the contract terms.
-demands must be expressed and reasonable
4Substantial Performance
One of the party fulfills enough of its contract to warrant some payment
5If a party fails to perform substantially.....
-receives nothing from the contract
-only recovers the value of the work, if any
6When is performance substantial? Courts look at:
1. How much benefit has the promisee received
2. If construction contract, can owner use the thing for intended purpose?
3. Can the promisee be compensated with money damages?
4. Did promisor act in good faith?
7promisee
to whom a promise is made
9Good Faith
Parties to a contract must carry out their obligations in good faith.
10Time of the Essence Clause
-Generally make contract dates strictly enforceable
-including a date doesn't make time of the essence and both parties are entitled to reasonable days.
-Must state that prompt performance is essential
-Courts dislike b/c short delay means no money
11Breach
When one party breaches a contract, the other party is discharged.
12Material breach
-breach that substantially harms the innocent party and for which it would be hard to compensate without charging the contract.
ex: Diamond seller does not give the jewelry store the diamonds they purchased. Jewelry store cannot make wedding rings.
13Courts will only discharge a contract if a party committed.....
a material breach
14Statue of Limitations
A time limit an injured party must file suit.
-Time begins at time of injury
15True Impossibility
Something has happened making it literally impossible to what the promisor said he would do.
16True Impossibility 3 causes:
1. Destruction of subject matter
2.Death of Promisor
3.Illegality
17Commercial Impracticability
-event has occurred that neither party anticipated
-fulfilling the contract would now be extraordinarily difficult and unfair to one party
18Frustration of Purpose
-event has occurred that neither party anticipated
-contract now has no value
19Courts consider when deciding impracticability and Frustration claims:
1. financial difficulties will never suffice to discharge contract.
2. Different means to accomplish task is expensive
3. Truly unexpected
20Remedy
method a court uses to compensate an injured party
21interest
a legal right in something
22expectation interest
-what the injured party reasonably thought the would get from the contract.
-typically is the profit the plaintiff would've earned
23Goal of expectation interest
put injured party in the position they would have been if both parties had fully performed their obligations.
24Direct Damages
Damages that flow from directly from the contract
25Consequential Damages
reimburse for harm that results from particular circumstances of the plaintiff
26Court will award consequential damages:
1. lost profits were foreseeable
2. plaintiff provides enough information so fact finder can reasonably estimate a fair amount
27Reliance Interest
-designed to put an injured party in position he would have been in had the parties never entered into a contract
-focuses on time and money the injured party spent performing his part of the agreement.
28Restitution Interest
designed to return to the injured party a benefit he has conferred on the other party
29Specific Performance
-When money damages are inadequate to compensate the injured party
-a court may order a party to perform under circumstances.
30Specific Performance only in cases involving:
-sale of land or
-asset that is considered unique
31Injunction
An order NOT to do something
32Preliminary injunction
an order prohibiting a party from doing something during a lawsuit
33Mitigation of Damages
Injured party must try to prevent unnecessary loss
34Mitigate
To keep damages as low as is reasonable
35Liquidated Damages
A clause stating in advance how much a party must pay if it breaches
36Courts enforce a liquidated damages clause if:
1. At the time of creating a contract, it was difficult to estimate actual damages.
2. the liquidated amount is reasonable