1For Roadway
what type of shovel must be used when collecting a road sample?
square nose or a template
2when collecting a roadway sample, what must be included/exluded from the mix?
include: all fines , exclude: underlying material (do not disturb)
3what makes for a good container for a roadway sample?
a non-absorbant & insulated container for transport
4what is the final step for roadway samples, stockpiles and streams?
label the container (Material type, ID#, JMF, Date, Time and Location)
5what does JMF mean?
Job Mix Formula (mix design)
6before collecting sample from a stockpile, what must be done?
remove 4 inches from the surface of the stockpile step (the blacked out area)

7what are needed to make a step in the stockpile?

a board and shovel
8where should you collect at least 1 scoop from in a step on a stockpile?
top, middle, bottom
9in a stockpile
how do you get your sample?

combine the top, middle and bottom
10when collecting from streams, how do you obtain your sample?
take 3 roughly equal parts from the chute bucket and combine